Project Description: The first phase of New Castle’s CSO Long-Term Control Plan (LTCP) included a large sewer separation project that included the placement of approximately 14,000 feet of new storm sewer (ranging from 12 to 60 inches in diameter) with 2,000 feet of new sanitary sewer.  The project dramatically improved storm drainage for the community and mitigated the impact of the CSOs.  Roadway, sidewalk, and ADA improvements were also made as part of the project.

Approximate Project Cost: $7,000,000

Breadth of Services Provided: CSO LTCP Preparation, Financing Assistance, Design Engineering, Land Acquisition Assistance, Bid Assistance, Construction Administration/Periodic Inspection, Post-Construction Monitoring