CLIENT:
|
Indiana
Department of Transportation
|
| |
|
PROJECT
LIMITS :
|
The
project limits include 2.93 miles of added travel
lanes on I-80/94, three interchange modifications,
and four INDOT Structures.
|
| |
PROJECT
SCHEDULE :
|
Start
Plan Development :
December 5, 2002
Final Tracings Submitted :
May 19, 2003
Letting : August 12, 2003
|
| |
APPROXIMATE
CONSTRUCTION COST:
|
$
55,500,000
|
| |
| SERVICES
PROVIDED BY UNITED: |
Design
– Road, Bridge and Signing, Contract Documents,
Permits, Bid Support, Post Bid Plan Review, Final As-Built
Plan Review
|
|
|
| PROJECT
SCOPE : |
The
project scope includes design of the added travel lanes
from Calumet Avenue to just west of Cline Avenue. The
added travel lanes included the four lanes of traffic
in each direction with continuous auxiliary lanes between
interchanges.
The
design included three interchange modifications: I-80/94
and Calumet Avenue, I-80/94 and Indianapolis Avenue,
and I-80/94 and Kennedy Avenue.
The
design of the replacement bridges: I-80/94 over Northcote
Avenue (Structure No. I-80-2-8472), I-80/94 over Eric-Lackawanna
Trail (Structure No. I-80-2-8471), I-80/94 over Indianapolis
Avenue (Structure No. I-80-2-8470), and I-80/94 over
CSX/IHB Railroad (Structure No. I-80-2-8469).
The
design also included complex signing, ITS, and noise
barriers.
|
|