I-80 BORMAN EXPRESSWAY
DESIGN / BUILD PROJECT - PHASE III-A

 

Borman Expressway - Phase III-A

 

CLIENT:

Indiana Department of Transportation
 

PROJECT LIMITS :

The project limits include two interchange modifications, and three INDOT Bridges. The road reconstruction was 2434 feet for Grant Street, 2388 feet for Broadway Street, and 1800 feet for Martin Luther King Street.
 

PROJECT SCHEDULE :

Start Plan Development :
December 5, 2002


Final Tracings Submitted :
September 2, 2003


Letting : December 19, 2003

 

APPROXIMATE CONSTRUCTION COST:

$ 21,500,000

 
 
PROJECT SCOPE :

The project scope includes design of two interchange modifications: I-80/94 and Grant Street, and I-80/94 and Broadway Street.

The design of the replacement bridges: Grant Street over I-80/94 (Structure No. I-80-9-8091), Broadway Street over I-80/94 (Structure No. 53-45-8466), and Martin Luther King Street over I-80/94 (Structure No. I-80-11-8056).

The design also included unsuitable soil remediation, complex signing, and noise barriers

 
 
SERVICES PROVIDED BY UNITED:

Design – Road and Signing, Contract Documents, Permits, Bid Support, Post Bid Plan Review, Final As-Built Plan Review

     

 

 

MORE ROAD PROJECTS . . . (Click on Pictures to View)

 

96th Street

96th Street
Emerson Avenue

Emerson Avenue
Mount Comfort Road

Mount Comfort Road

 

 

Olio Road

Olio Road
Rush CR 700 W

Rush CR 700 W

I-465 Interchange Modification

I-465 Interchange Modification

     
I-65 Design / Build

I-65 Design / Build
   

 

 

 

BACK TO ROAD SERVICES / SITE NAVIGATION

BACK TO HOME

 

 


1625 NORTH POST ROAD  
PHONE: 317-895-2585
INDIANAPOLIS, INDIANA 46219  
FAX: 317-895-2596

 

E-Mail United : info@ucea.com

 

 

 

Copyright © 2005, 2006, 2007 United Consulting Engineers & Architects. All Rights Reserved.